AIRPORTS

BOLZANO
Location: Bolzano (Italy)
Sector: Aviation
Year: 2010-2012
Project Area: 1,800 sqm
Client: ABD Dolomiten SpA
Scope of work: Masterplan - Preliminary Project
Amount: 5 millions
Description: Bolzano airport terminal expansion and redevelopment project. The project is carried out in harmony with the natural landscape of Bolzano with extensive use of glazing necessary to reflect the mountainous and wooded environment of the site.
RAFO ADAM MILITARY AIRBASE
Location: Adam Airbase
Sector: Aviation
Year: 2013-2018
Project Area: 2,410 acre
Client: Hill International on behalf of Oman Ministry of defence
Scope of work: Preliminary and definitive project - Aviation consultancy
Amount: Confidential
Description: Realization of the flight infrastructure of Adam Air Base. the runway was equipped with bracking devices (aresting cable), aircraft isolation areas and new runway thresholds. All taxiways and aprons required for aircraft handling and parking were designed.
MUSCAT AIRPORT SOUTH AIRFIELD REFURBISHMENT
Location: Muscat (Oman)
Sector: Aviation
Year: 2013-2018
Project Area: 720 acre
Client: Hill International on behalf of Ministry of Transport & Communications
Scope of work: Definitive Project - Aviation Consultancy
Amount: 42 millions
Description: Because of the needs to adjust at ICAO code F the Airfield South of Muscat International Airport, this intervention consisted of upgrading to ICAO class F the taxiway parallel to the runway through an enlargement of the load-bearing pavement of the taxiway and widening of the shoulders. The existing pavement was also upgraded by recycling the base and revamping the binder and the surface layer. The work also included the construction of eight new Rapid Exit Taxiways, the lengthening of one of the two heads and the construction of additional Slow Exit Taxiways. The greatest difficulty was reconciling the work with the operation of the manoeuvring area since the northern runway was not yet tested. The work was planned phasing it in 18 different work steps (some depicted on the right). Finally, the design include the implementation of an A-SMGCS system. Our designing company took care of the executive design, on-site assistance to the works and remote assistance to ensure that the drawings were constantly updated.
ROMA URBE GENERAL AVIATION HANGAR
Location: Rome (Italy)
Sector: Aviation
Year: 2014
Project Area: 1,000 sqm
Client: ENAC (Italian Civil Aviation Authority)
Scope of work: Preliminary and Definitive Project
Amount: 1,5 millions
Description: Design of a general aviation hangar structural upgrading. The original hangar was designed by famous architect/engineer Pierluigi Nervi in the 1960s. The retrofitting project is related to compliance with eartquake regulations.
AKWA IBOM INTERNATIONAL AIRPORT
Location: Uyo (Nigeria)
Sector: Aviation
Year: 2015
Project Area: 20 acre
Client: Alcon Nig LTD
Scope of work: Definitive Project
Amount: 5 millions
Description: Realization of the flight infrastructure of Adam Air Base. the runway was equipped with bracking devices (aresting cable), aircraft isolation areas and new runway thresholds. All taxiways and aprons required for aircraft handling and parking were designed.
CORTINA D'AMPEZZO AIRPORT
Location: Cortina d'Ampezzo (Italy)
Sector: Aviation
Year: 2018-2019
Project Area: 1,000 sqm
Client: Cortina d'Ampezzo Municipality Administration
Scope of work: Masterplan
Amount: 20 millions
Description: Cortina d'Ampezzo airport development project. Realization of a new terminal and lengthening of the runway. The project is among the projects planned for the Milan and Cortina 2026 Winter Olympics Games
PESCARA
Year: 2017
Pescara Airport Runway Extension definitive and construction Project
Amount: 4,5 millions
Client: SAGA S.p.A.
BOLZANO AIRPORT RUNWAY EXTENSION
Location: Bolzano (Italy)
Sector: Aviation
Year: 2018-2020
Project Area: 115,000 sqm
Client: ABD Dolomiten SpA
Scope of work: Definitive Project - Works supervision
Amount: 3,5 millions
Description: Runway lengthening and runway strip load bearing capacity adjustment. Project aimed at increasing airport safety standards and increasing flight capacity.
SALERNO AIRPORT RUNWAY EXTENSION AND AIRFIELD DEVELOPMENT
Location: Salerno (Italy)
Sector: Aviation
Year: 2018-2020
Project Area: 225 acre
Client: GESAC SpA (Naples Airport)
Scope of work: Definitive Project - Aviation Consultancy
Amount: Confidential
Description: This intervention was done to allow the development of Naples Airport. Salerno is a city a few dozen kilometres from Naples and had a General Aviation airport only. The growing demand for traffic at Naples airport made it necessary to develop Salerno airport in order to transfer part of the flights that could no longer be handled in Naples. The project therefore included the adaptation of the runway to an instrument runway, the upgrading of taxiways and be construction of a new apron.
VENEZIA
Year: 2018 - 2024
Preliminary project for the installations required for the positioning of new PCAs and 400Hz columns
Amount: 20 millions
Client: SAVE S.p.A.
VENEZIA
Year: 2018
Definitive and construction project for the installations required for the positioning of new PCAs and 400Hz columns in front of Cargo area
Amount: 6 millions
Client: SAVE S.p.A.
ZUNYI AIRPORT TERMINAL AND AIRSIDE MASTERPLAN
Location: Zunyi (China)
Sector: Aviation
Year: 2018
Project Area: 560 acre
Amount: Confidential
Client: Chinise Government
Scope of work: Masterplan
Description: The airport is situated in the scenic spot of Zunyi, where the waves are shining. The plan fully demonstrates the beautiful and magnificent natural environment and the characteristics of sustainability of the project. The goal is to make the airport a landmark gateway to Zunyi and even Guizhou Province, and to attract tourists from all over the world with enthusiasm.
PARMA
Year: 2019
Definitive and construction project, supervision of works for increasing of runway, strip and R.E.S.A. loading bearing of Parma “Giuseppe Verdi” Airport
Amount: 3,6 millions
Client: So.Ge.A.P. S.p.A.
SARANDA AIRPORT DEVELOPMENT
Location: Saranda (Albania)
Sector: Aviation
Year: 2019-2021
Project Area: 385 acre
Amount: 60 millions
Client: SEA SpA (Milan Airport)
Scope of work: Masterplan - Preliminary Project - Aviation Consultancy
Description: Project for a new civil aviation airport lcoated in southern Albania. The project involves the construction of a 2500m runway and short-to-medium-range aircraft. The project is linked to the tourist development of the locality, located in the vicinity of Greece and the island of Corfu.
BOLOGNA AIRPORT APRON EXTENSION
Location: Bologna (Italy)
Sector: Aviation
Year: 2021-2025
Project Area: 37,000 sqm
Client: Aeroporto di Bologna SpA
Scope of work: Definitive Project - Works supervision
Amount: 19 millions
Description: Design and leading works of construction of a new cargo and passenger apron for ICAO Class E aircraft. The Project concerns the construction of complex drainage systems and concrete pavement apron for aicraft up to 340 tonnes MTOW. Scope of the works:
- New 40,000 qm Apron and new connection taxiways;
- Neew AGL Systems;
- Aeronautical Assesments and simulations;
- Rainwater collection systems;
Lighting study of aprons and design of new light masts.